Critical path analysis

HSC Maths Standard 2 · Unit 5: Networks

Critical path analysis notes

Fact-checked by a second, independent AI review.

Key ideas and terms for identifying the critical path, floats, and timing in a project network, with how to answer typical NSW HSC questions.

Critical path
The sequence of activities with zero slack that sets the project duration.
Slack/float
The amount of time an activity can be delayed without delaying the project; zero slack means the activity is critical.
Earliest start/finish (ES/EF)
The earliest times an activity can start and finish based on predecessors.
Latest start/finish (LS/LF)
The latest times an activity can start and finish without delaying the project, derived from the project end.
Network diagram
A diagram of activities (nodes or arrows) and dependencies used to compute ES/EF, LS/LF and floats; helps identify the critical path.

Remember it: Follow the path where every link has no slack—the Critical Path is the chain that must not slip.

Exam tip: Markers check clear definitions, correct ES/EF/LS/LF calculations, correct identification of the critical path, and correct interpretation of slack/impact on project duration.

Syllabus checklist

  • Critical path analysis: core ideas
  • Terms and typical exam questions for "Networks" in NSW HSC Mathematics Standard 2

Practice questions

  1. 1. In a network, the critical path is the path with the

    Answer checked

    Show answer

    Answer: longest duration. The critical path has the longest total duration through the network.

  2. 2. A task on the critical path has zero slack.

    Answer checked

    Show answer

    Answer: True. Critical-path tasks must start on time and finish on time, giving them zero slack.

  3. 3. In a small network, the start-to-finish durations are: path A→B→D = 6 days; path A→C→D = 5 days. The critical path duration is ____ days.

    Answer checked

    Show answer

    Answer: 6. The longer path determines the project duration, which is 6 days.

  4. 4. In the network with A→B (2 days), B→C (3 days), and A→C (5 days), the project’s earliest finish time is ____.

    Answer checked

    Show answer

    Answer: 5. Both paths A→C and A→B→C take 5 days, so the earliest finish is 5.