Critical path analysis
HSC Maths Standard 2 · Unit 5: Networks
Critical path analysis notes
Fact-checked by a second, independent AI review.
Key ideas and terms for identifying the critical path, floats, and timing in a project network, with how to answer typical NSW HSC questions.
- Critical path
- The sequence of activities with zero slack that sets the project duration.
- Slack/float
- The amount of time an activity can be delayed without delaying the project; zero slack means the activity is critical.
- Earliest start/finish (ES/EF)
- The earliest times an activity can start and finish based on predecessors.
- Latest start/finish (LS/LF)
- The latest times an activity can start and finish without delaying the project, derived from the project end.
- Network diagram
- A diagram of activities (nodes or arrows) and dependencies used to compute ES/EF, LS/LF and floats; helps identify the critical path.
Remember it: Follow the path where every link has no slack—the Critical Path is the chain that must not slip.
Exam tip: Markers check clear definitions, correct ES/EF/LS/LF calculations, correct identification of the critical path, and correct interpretation of slack/impact on project duration.
Syllabus checklist
- Critical path analysis: core ideas
- Terms and typical exam questions for "Networks" in NSW HSC Mathematics Standard 2
Practice questions
1. In a network, the critical path is the path with the
Answer checked
Show answer
Answer: longest duration. The critical path has the longest total duration through the network.
2. A task on the critical path has zero slack.
Answer checked
Show answer
Answer: True. Critical-path tasks must start on time and finish on time, giving them zero slack.
3. In a small network, the start-to-finish durations are: path A→B→D = 6 days; path A→C→D = 5 days. The critical path duration is ____ days.
Answer checked
Show answer
Answer: 6. The longer path determines the project duration, which is 6 days.
4. In the network with A→B (2 days), B→C (3 days), and A→C (5 days), the project’s earliest finish time is ____.
Answer checked
Show answer
Answer: 5. Both paths A→C and A→B→C take 5 days, so the earliest finish is 5.