Planning & scheduling
WACE Maths Applications · Unit 3: Networks
Planning & scheduling notes
Fact-checked by a second, independent AI review.
Overview of networks in planning and scheduling. You model activities and dependencies using network diagrams (AON or AOE), and use paths to find the critical sequence that drives the project finish time.
- Activity-on- node vs Activity-on-edge (AON/AOE)
- In standard CPM/PERT terminology, two forms exist: AOE (Activity-on-Edge) where activities are arrows (edges) between event nodes and durations are shown on the arrows; AON (Activity-on-Node) where activities are represented by nodes (events) and durations are associated with the node, with dependencies shown by connecting arrows.
- Event/Node
- An event represents a project moment where activities start or finish.
- Critical path and float
- The longest path from start to finish sets the project duration; float is the time an activity can slide without delaying the finish.
- Earliest Start/Finish and Latest Start/Finish
- Compute when activities can begin/finish without delaying the project, and use these to find slack.
- Dummy activities
- Use dummy activities to show dependency where no time is added but a precedence relation exists.
Remember it: Remember: the critical path is the 'do or die' route; if it moves, the project date moves.
Exam tip: Markers want correct identification of the critical path, correct calculation of earliest/latest times, float, and understanding of when dummy activities are needed; show labelled diagrams and clear step-by-step calculations.
Syllabus checklist
- Planning & scheduling: core ideas
- Terms and typical exam questions for "Networks" in WACE ATAR Mathematics Applications
Practice questions
1. The critical path is the sequence of activities with the longest total duration.
Answer checked
Show answer
Answer: True. The critical path has zero total slack; it is the longest-duration path.
2. An activity's earliest start time depends on the finish of its ____ activities.
Answer checked
Show answer
Answer: predecessors. It depends on the finish of its immediate predecessors.
3. If an activity has a slack of 2 days, it can start 2 days later without delaying the project.
Answer checked
Show answer
Answer: True. Positive slack means some delay is possible without affecting the finish date.

Practise planning & scheduling as a game
Hearts, combos, streaks and an AI tutor that explains every answer. Start free.