Development approaches

HSC Software Engineering · Unit 5: Software project

Development approaches notes

Fact-checked by a second, independent AI review.

Overview of common software development approaches used in NSW HSC Software Engineering, focusing on core concepts, benefits, drawbacks and typical exam question angles.

Waterfall
Linear, sequential process with fixed requirements and milestones; little customer involvement after design phase; risks when requirements change.
Iterative/Incremental
Builds in small iterations; each increment adds functionality; easier to adapt but requires good planning and integration.
Spiral
Risk-driven model combining iterative development with systematic risk analysis; repeated cycles of planning, design, prototyping, and evaluation; suitable for large, complex projects with evolving requirements.
Agile (incl. Scrum and XP)
Emphasises flexible planning, customer collaboration, rapid delivery in short sprints; high adaptability and frequent feedback.
Prototyping
Create a working model to clarify requirements; reduces misinterpretation but may lead to scope creep if not controlled.
Rapid Application Development (RAD)
Speed-focused approach using prototyping, reuse, and user involvement to shorten delivery time; can compromise architecture if overemphasised.

Remember it: WASP-RAID: Remember WASP for Waterfall, Agile, Spiral, Prototyping; RAD adds Iteration and Deployment considerations.

Exam tip: Markers look for: clear definition of each approach, suitable contexts, trade-offs, and how projects choose between them; include examples, risks, and how you manage change and stakeholder involvement.

Syllabus checklist

  • Development approaches: core ideas
  • Terms and typical exam questions for "Software project" in NSW HSC Software Engineering

Practice questions

  1. 1. In the V-model, testing activities follow each corresponding development phase.

    Answer checked

    Show answer

    Answer: True. The V-model links each development phase with a matching testing phase.

  2. 2. The approach that models the system as a sequence of iterations delivering executable increments is called ____.

    Answer checked

    Show answer

    Answer: iterative development. Iterative development describes this cyclic, incremental process.

  3. 3. Which development approach uses a formal, sequential phases with extensive up-front design?

    Answer checked

    Show answer

    Answer: Waterfall. Waterfall proceeds through defined phases with upfront design.

  4. 4. In Scrum, sprints are typically fixed to __ weeks.

    Answer checked

    Show answer

    Answer: 2. A common sprint duration is 2 weeks in Scrum.