Project management
HSC Software Engineering · Unit 5: Software project
Project management notes
Fact-checked by a second, independent AI review.
Overview of how software projects are planned, tracked and controlled in NSW HSC Software Engineering. Focus on scope, schedule, cost, quality, risk and change management with typical exam prompts.
- Project scope
- Defines what the project will deliver and what is out of scope; scope creep is a common risk if not managed.
- Stakeholders and requirements
- Identify all affected parties and gather requirements; ensure clear, testable acceptance criteria.
- Work breakdown structure (WBS) and tasks
- Decompose the project into smaller tasks; assigns responsibility and establishes a basis for scheduling.
- Scheduling and milestones
- Use Gantt or other tools to plan timelines; set milestones to track progress and trigger reviews.
- Risk and change management
- Identify risks, assess impact, plan mitigations; implement formal change control to manage scope and cost.
Remember it: Think: Scope, Stakeholders, Structure, Schedule, and Scrutiny (SSSS) to remember core PM steps.
Exam tip: Markers expect clear definitions of terms, link between planning outputs (scope, WBS, schedule) and project controls (risk, change control), plus apply ideas to scenario questions with trade-offs.
Syllabus checklist
- Project management: core ideas
- Terms and typical exam questions for "Software project" in NSW HSC Software Engineering
Practice questions
1. Which item best describes a Gantt chart in project management?
Answer checked
Show answer
Answer: timeline with tasks. A Gantt chart shows tasks on a timeline with durations and sequencing.
2. The critical path in a project schedule has the longest duration.
Answer checked
Show answer
Answer: The statement is True. The critical path determines the project duration by the longest time to complete dependent tasks.
3. A _____ is a breakdown of project work into deliverable components.
Answer checked
Show answer
Answer: WBS. WBS stands for Work Breakdown Structure, detailing deliverables and tasks.
4. In risk planning, compute expected value: probability 0.2, impact 50k.
Answer checked
Show answer
Answer: 10k. Expected value = probability × impact = 0.2 × 50k = 10k.
5. Identify the formal approved plan used to control scope and schedule.
Answer checked
Show answer
Answer: Baseline. The baseline is the approved plan for scope, schedule, and budget.