Critical path

QCE General Maths · Unit 3: Networks & decision maths

Critical path notes

Fact-checked by a second, independent AI review.

Critical path is the longest duration path through a network, determining the project finish time and the slack of other activities. You use forward and backward passes to find earliest start/finish, latest start/finish, and identify the critical activities.

Network diagram
A directed graph of activities with durations; arrows show tasks and nodes show events or milestones.
Forward pass
Calculate earliest start (ES) and earliest finish (EF) for each activity from the start node.
Backward pass
Calculate latest start (LS) and latest finish (LF) for each activity from the end node, working backwards.
Slack and critical path
Slack = LS − ES (or LF − EF); activities with zero slack form the critical path.
Typical exam tasks
Identify the critical path, compute ES/EF, LS/LF, and slack; determine project duration and how changes affect the path.

Remember it: Remember CPM: Critical Path Makes Projects Move, zero slack means a task on the route to the finish.

Exam tip: Markers check clear definitions of forward/backward pass, correct calculation of ES/EF/LS/LF, correct identification of zero-slack activities, and the final project duration with an explicit critical path.

Syllabus checklist

  • Critical path: core ideas
  • Terms and typical exam questions for "Networks & decision maths" in QCE General Mathematics

Practice questions

  1. 1. In the network A->B, A->C, both to D. Durations A=3, B=4, C=5, D=2. What is the critical path and its duration?

    Answer checked

    Show answer

    Answer: A-C-D (10). Paths A-B-D and A-C-D have totals 9 and 10; the longest (critical) path is A-C-D with duration 10.

  2. 2. The critical path has zero slack.

    Answer checked

    Show answer

    Answer: True. By definition, activities on the critical path have zero slack.

  3. 3. Early finish time of D is ____

    Answer checked

    Show answer

    Answer: 10. EF(D) = ES(D) + duration(D) = 8 + 2 = 10; D sits on the critical path.

  4. 4. True/False: A task with zero slack is on the critical path.

    Answer checked

    Show answer

    Answer: True. Zero slack means the task lies on the critical path.

  5. 5. Which is the latest start time for B?

    Answer checked

    Show answer

    Answer: 4. B must start such that EF(B)=LS(B)+4 ≤ 8, giving LS(B)=4.