Critical path
QCE General Maths · Unit 3: Networks & decision maths
Critical path notes
Fact-checked by a second, independent AI review.
Critical path is the longest duration path through a network, determining the project finish time and the slack of other activities. You use forward and backward passes to find earliest start/finish, latest start/finish, and identify the critical activities.
- Network diagram
- A directed graph of activities with durations; arrows show tasks and nodes show events or milestones.
- Forward pass
- Calculate earliest start (ES) and earliest finish (EF) for each activity from the start node.
- Backward pass
- Calculate latest start (LS) and latest finish (LF) for each activity from the end node, working backwards.
- Slack and critical path
- Slack = LS − ES (or LF − EF); activities with zero slack form the critical path.
- Typical exam tasks
- Identify the critical path, compute ES/EF, LS/LF, and slack; determine project duration and how changes affect the path.
Remember it: Remember CPM: Critical Path Makes Projects Move, zero slack means a task on the route to the finish.
Exam tip: Markers check clear definitions of forward/backward pass, correct calculation of ES/EF/LS/LF, correct identification of zero-slack activities, and the final project duration with an explicit critical path.
Syllabus checklist
- Critical path: core ideas
- Terms and typical exam questions for "Networks & decision maths" in QCE General Mathematics
Practice questions
1. In the network A->B, A->C, both to D. Durations A=3, B=4, C=5, D=2. What is the critical path and its duration?
Answer checked
Show answer
Answer: A-C-D (10). Paths A-B-D and A-C-D have totals 9 and 10; the longest (critical) path is A-C-D with duration 10.
2. The critical path has zero slack.
Answer checked
Show answer
Answer: True. By definition, activities on the critical path have zero slack.
3. Early finish time of D is ____
Answer checked
Show answer
Answer: 10. EF(D) = ES(D) + duration(D) = 8 + 2 = 10; D sits on the critical path.
4. True/False: A task with zero slack is on the critical path.
Answer checked
Show answer
Answer: True. Zero slack means the task lies on the critical path.
5. Which is the latest start time for B?
Answer checked
Show answer
Answer: 4. B must start such that EF(B)=LS(B)+4 ≤ 8, giving LS(B)=4.