Network basics (nodes, edges, weighted graphs)
Identify the diagram’s nodes (points) and edges (connections), and note any weights (costs or times) that affect calculations.
Shortest path
Find the minimum-cost or minimum-time path between two nodes using weighted graphs; Dijkstra's algorithm is commonly taught and works with non-negative weights.
Critical Path Method (CPM) / PERT
Model a project with tasks as edges (activities) and durations as weights; CPM computes the critical path to determine the earliest possible project duration, while PERT uses three-point estimates (optimistic, most likely, pessimistic) to handle uncertainty.
Decision tables and matrices
Organise options against criteria, compute scores or expected values to choose the best option.
Linear programming (brief intro)
Set up objective and constraints to optimise a quantity (e.g., cost, profit) within feasible limits.

Remember it: “N-E-T” for networks: Nodes, Edges, Time (cost) — follow the path to the answer.

Exam tip: Show clear labels, state method used (shortest path, CPM/PERT, or decision analysis), write the final result with units, and explain what the result means for the real problem.

Syllabus checklist

  • Assignment: core ideas
  • Terms and typical exam questions for "Networks & decision maths" in QCE General Mathematics

Practice questions

  1. 1. In a network, the shortest path between A and B is defined as the path with the smallest sum of weights.

    Answer checked

    Show answer

    Answer: Smallest total weight. Shortest path minimizes the sum of edge weights along the path.

  2. 2. In Prim's algorithm, the set of chosen edges always forms a tree.

    Answer checked

    Show answer

    Answer: True. Prim's algorithm grows a spanning tree by adding the lightest edge that connects to the tree.

  3. 3. A minimum spanning tree of a graph with V vertices has exactly ____ edges.

    Answer checked

    Show answer

    Answer: V-1. A spanning tree on V vertices has V-1 edges.

  4. 4. In a PERT/CPM network, the critical path is the sequence of activities with the longest total duration.

    Answer checked

    Show answer

    Answer: True. The critical path has the longest duration and determines the project finish time.

  5. 5. For a graph with V = 5, a spanning tree has exactly ____ edges.

    Answer checked

    Show answer

    Answer: 4. A spanning tree on 5 vertices has 4 edges.